CONSIDER
CONTRACT AMENDMENT WITH RAMLIT ASSOCIATES FOR COMPUTER MODELING ASSISTANCE
(CVSIM) |
||
|
|||
Meeting Date: |
July 19, 2004 |
Budgeted: $6,000 for combined tasks |
|
|
|||
Staff Contact: |
Henrietta Stern |
Program No.: 1-1-1 and 1-1-2 |
|
|
|
Cost Estimate: not to exceed $6,000 |
|
|
|||
General Counsel
Approval: N/A |
|||
Committee
Recommendation: The Administrative
Committee reviewed this item on July12, 2004 and recommended approval. |
|||
CEQA Compliance: N/A |
|||
SUMMARY: The District annually retains RAMLIT Associates for assistance with CVSIM computer model maintenance, quality control and specific modeling requests associated with water supply projects and planning, as shown in Exhibit 5-A. RAMLIT is paid only for tasks authorized by the General Manager on an as-needed basis. The Board will consider renewing RAMLIT’s existing contract to provide for services in fiscal year (FY) 2004-2005 for a not-to-exceed amount of $6,000. The contract with RAMLIT will specify that the $6,000 is to be allocated in the following manner, in accordance with the FY 2004-2005 budget adopted by the Board at its June 21, 2004 meeting:
Program No. |
Task |
Not-to-Exceed Amount ($) |
Account No. |
1-1-1 |
CVSIM Update/Assistance |
$ 3,000 |
5-7829 |
1-1-2 |
CVSIM Quality Control |
$ 3,000 |
5-7829 |
|
TOTAL |
$ 6,000 |
|
The $6,000 maximum amount is $15,000 lower than the total amount approved for last year. No expenditures are considered to be reimbursable by California-American Water (Cal-Am).
RECOMMENDATION: Staff recommends that the Board approve this item along with the consent calendar. The Administrative Committee reviewed this item at its July 12, 2004 meeting and voted 3 to 0 to recommend approval. If this item is adopted along with the Consent Calendar, staff will execute a contract amendment for a not-to-exceed amount of $6,000 for this work.
5-A RAMLIT Associates Scope of Work and Fee Schedule for FY 2005
U:\staff\word\boardpacket\2004\2004boardpacket\20040719\ConsentCalendar\05\item5.doc